140 Fulton Street
Electrical manpower loading & schedule plan
This is the quick view, shown because this viewer can’t run the interactive plan. Open the file in Safari, Chrome or Edge for the live 3D model you can turn and the issued PDF and Excel.
Peak crew
31 men
Mar 2028
Duration
31 mo
Jan ’27 – Jul ’29
Worker-months
434
27 scopes
Crew at peak
5 / 26 / 0
Foremen / journeymen / apprentices
Electrical crew by month
Men on site each month, stacked by area. Gold flags are schedule milestones.
0102030402027M1JulM2202831M3JulM42029M5M6JulM7
0102030402027M1AprJulM2Oct202831AprM3JulOctM42029M5M6AprJulM7
Building · 298 worker-moResidential · 106 worker-moComm/Amenity · 30 worker-mo
M1 Mobilization / temp service · Jan ’27M2 Superstructure start · Jul ’27M3 Top out · Jun ’28M4 Temp w/ permanent · Dec ’28M5 Permanent power · Jan ’29M6 EM power · Mar ’29M7 TCO · Jul ’29
Where the crews are
The tower in 3D, built to the GC deck. Each numbered badge is a crew; the count beside each floor is men on that floor.
Jan 2027 · 3 men on site
3D building elevation, Jan 2027: 3 men on site, crews numbered by scope
3D · Jan 2027
  • 01
    Temp service
    Site / street front
    3 men
Dec 2027 · 20 men on site · GC deck at L18
3D building elevation, Dec 2027: 20 men on site, crews numbered by scope
3D · Dec 2027
  • 04
    Slab embeds / deck rough
    L16–L20
    4 men
  • 02
    Temp light & power
    L11–L14
    2 men
  • 06
    Risers / feeders
    L9–L12
    4 men
  • 20
    Apartment rough-in L5-20
    L5–L9
    8 men
  • 24
    Base rough-in (cellar-L4)
    L3–L4
    2 men
Mar 2028 · 31 men on site · GC deck at L28
3D building elevation, Mar 2028: 31 men on site, crews numbered by scope
3D · Mar 2028
  • 04
    Slab embeds / deck rough
    L26–L30
    4 men
  • 06
    Risers / feeders
    L18–L21
    4 men
  • 02
    Temp light & power
    L17–L20
    2 men
  • 20
    Apartment rough-in L5-20
    L16–L20
    8 men
  • 12
    Pulling & terminations
    L13–L19
    4 men
  • 08
    Tap panels TDP-6 / DP-10 / DP-13 / TDP-16
    L6–L11
    4 men
  • 10
    Fire pump feeders / FP room
    L1–L3
    3 men
  • 13
    Generator / EDP-GEN
    L1
    2 men
Oct 2028 · 20 men on site
3D building elevation, Oct 2028: 20 men on site, crews numbered by scope
3D · Oct 2028
  • 26
    Roof / EMR / bulkhead power
    Roof
    2 men
  • 25
    L38 amenity / L39 elec room
    L38–L39
    2 men
  • 22
    Closet fit-outs / unit panels (99)
    L32–L37
    2 men
  • 02
    Temp light & power
    L33–L36
    2 men
  • 27
    Stairwells & corridors
    L10–L20
    2 men
  • 14
    Fire alarm - FCC, risers, devices
    Cellar–L6
    2 men
  • 05
    Vault 301 / NP fit-out
    L3
    8 men
Scopes
Crew per month for each scope (darker = more men).
Building
01
Temp service
Site / street front
peak 3
Jan ’27 – Jan ’273 worker-mo
02
Temp light & power
Follows the deck, floor by floor
peak 2
Jul ’27 – Dec ’2836 worker-mo
03
Con Ed duct banks / splice chambers
Cellar, Fulton St side
peak 4
Apr ’27 – Aug ’2720 worker-mo
04
Slab embeds / deck rough
Each slab pour, cellar to roof
peak 4
Jul ’27 – Jun ’2848 worker-mo
05
Vault 301 / NP fit-out
Level 3, front west corner
peak 8
Oct ’28 – Dec ’2824 worker-mo
06
Risers / feeders
Riser shaft, Level 3 to 39
peak 4
Oct ’27 – Sep ’2848 worker-mo
07
L3 switchgear line-up (4000A SEB)
Level 3 switchgear room
peak 4
May ’28 – Jul ’2812 worker-mo
08
Tap panels TDP-6 / DP-10 / DP-13 / TDP-16
Levels 6, 10, 13, 16
peak 4
Mar ’28 – Apr ’288 worker-mo
09
750 kVA xfmr / ATS room
Level 3 switchgear + ATS rooms
peak 4
Jul ’28 – Aug ’288 worker-mo
10
Fire pump feeders / FP room
Level 3 to cellar fire pump room
peak 3
Mar ’28 – Apr ’286 worker-mo
11
Lightning protection
Roof / bulkhead
peak 2
Aug ’28 – Sep ’284 worker-mo
12
Pulling & terminations
Riser shaft + all panels
peak 4
Jan ’28 – Jul ’2828 worker-mo
13
Generator / EDP-GEN
Rear pit, roof over Level 1
peak 2
Mar ’28 – May ’286 worker-mo
14
Fire alarm - FCC, risers, devices
FCC at L1 lobby; stair riser; all floors
peak 5
Oct ’28 – Apr ’2920 worker-mo
15
Submetering
Electric closets, all residential floors
peak 2
Nov ’28 – Dec ’284 worker-mo
16
ARCS (FDNY radio)
Stairs + riser, all floors
peak 2
Feb ’29 – Mar ’294 worker-mo
17
Commissioning / testing
L3 power plant, generator, FA
peak 2
Apr ’29 – Jul ’298 worker-mo
18
Punchlist
All floors
peak 2
Apr ’29 – Jul ’298 worker-mo
19
Temp removal
All floors
peak 2
Jun ’29 – Jul ’293 worker-mo
Residential
20
Apartment rough-in L5-20
Levels 5-20
peak 8
Dec ’27 – Mar ’2832 worker-mo
21
Apartment rough-in L21-37
Levels 21-37
peak 8
May ’28 – Aug ’2832 worker-mo
22
Closet fit-outs / unit panels (99)
Elec closets + 99 units, L5-37
peak 2
Apr ’28 – Oct ’2814 worker-mo
23
Finish / trim (units)
Levels 5-37
peak 4
Nov ’28 – May ’2928 worker-mo
Comm/Amenity
24
Base rough-in (cellar-L4)
Cellar to Level 4 (lobby, amenity, BOH)
peak 2
Sep ’27 – Dec ’278 worker-mo
25
L38 amenity / L39 elec room
Levels 38-39
peak 2
Jul ’28 – Nov ’2810 worker-mo
26
Roof / EMR / bulkhead power
Roof, EMR, bulkhead
peak 2
Sep ’28 – Oct ’284 worker-mo
27
Stairwells & corridors
Stairs + corridors, all floors
peak 2
Sep ’28 – Dec ’288 worker-mo
Crew makeup
Foreman, journeymen and apprentices by month. NYS apprentice ratio 1:1, 1:3 — within ratio every month.
MonthMenGFFJWAppMax App
Jan 20273121
Apr 20274132
May 20274132
Jun 20274132
Jul 2027101184
Aug 2027101184
Sep 20278173
Oct 20271211104
Nov 20271211104
Dec 20272012177
Jan 20282213188
Feb 20282213188
Mar 202831142611
Apr 20282513219
May 202830142510
Jun 202828142310
Jul 202830142510
Aug 20282412218
Sep 2028161156
Oct 2028201197
Nov 20282211208
Dec 20282011187
Jan 20296152
Feb 20298173
Mar 2029111194
Apr 20291311115
May 20298173
Jun 20296152
Jul 20295142
Need-by register
What the electrical crew needs, from whom, and by when.
  • NB-01
    Temporary service approvals (SSP + NYCTA) and Con Ed temporary service
    Owner · needed Jan 2027 · Temp service: 3 men from Jan 2027 · 3 worker-months
    Due soon
  • NB-02
    First deck available for slab embeds (superstructure start)
    GC · needed Jul 2027 · Slab embeds / deck rough: 4 men from Jul 2027 · 48 worker-months
    Open
  • NB-03
    Deck turnover floor by floor, Cellar–Roof, for embeds and temp light & power
    GC · needed Jul 2027 · Slab embeds / deck rough: 4 men from Jul 2027 · 48 worker-months through Jun 2028
    Open
  • NB-04
    Riser shaft access L3–L39 (shaft clear, sleeves and openings set)
    GC · needed Oct 2027 · Risers / feeders: 4 men from Oct 2027 · 48 worker-months through Sep 2028
    Open
  • NB-05
    Cellar–L4 areas released for base rough-in (lobby, amenity, BOH)
    GC · needed Sep 2027 · Base rough-in (cellar-L4): 2 men from Sep 2027 · 8 worker-months through Dec 2027
    Open
  • NB-06
    Apartment floors released for rough-in, L5–L20
    GC · needed Dec 2027 · Apartment rough-in L5-20: 8 men from Dec 2027 · 32 worker-months through Mar 2028
    Open
  • NB-07
    Apartment floors released for rough-in, L21–L37
    GC · needed May 2028 · Apartment rough-in L21-37: 8 men from May 2028 · 32 worker-months through Aug 2028
    Open
  • NB-08
    Generator size decision: 250 kW vs 400 kW natural gas (E-301, 100% DD)
    Owner · needed Mar 2028 · Generator / EDP-GEN: 2 men from Mar 2028 · 6 worker-months
    Open
  • NB-09
    Level 3 switchgear and ATS rooms enclosed, dry and lockable
    GC · needed May 2028 · L3 switchgear line-up (4000A SEB): 4 men from May 2028 · 12 worker-months
    Open
  • NB-10
    Roof / bulkhead access for lightning protection and roof power
    GC · needed Aug 2028 · Lightning protection: 2 men from Aug 2028 · 4 worker-months
    Open
  • NB-11
    L38 amenity / L39 electrical room turnover
    GC · needed Jul 2028 · L38 amenity / L39 elec room: 2 men from Jul 2028 · 10 worker-months
    Open
  • NB-12
    FCC room at L1 lobby available for fire alarm head-end
    GC · needed Oct 2028 · Fire alarm - FCC, risers, devices: 2-5 men from Oct 2028 · 20 worker-months
    Open
  • NB-13
    Units ready for finish & trim (walls closed, painted), L5–L37
    GC · needed Nov 2028 · Finish / trim (units): 4 men from Nov 2028 · 28 worker-months through May 2029
    Open
  • NB-14
    Temp light & power re-feed from the permanent L3 service
    GC / Con Ed · needed Dec 2028 · Milestone month Dec 2028: 20 men on site across 6 scopes
    Open
  • NB-15
    Con Ed energizes Vault 301 / 4000A SEB (permanent power)
    Con Ed · needed Jan 2029 · Milestone month Jan 2029: 6 men on site across 2 scopes
    Open
  • NB-16
    Generator + ATS acceptance (EM power)
    Owner · needed Mar 2029 · Milestone month Mar 2029: 11 men on site across 3 scopes
    Open
OZZ Electric USA · 140 Fulton Street · Rev 0 · Plan fingerprint A7BE 1D39 732E 188C
This quick view is generated from the same plan data as the interactive app and contains no pricing.