Construction sequence · Version 6
Electrical & Fire Alarm Sequence
From temporary power in January 2027 to the certificate of occupancy in July 2029: every scope, floor by floor, with the crew on site each month.
39 stories
99 units
2:22 runtime
Download MP4
NowTitle
Mobilize
Jan 2027
Temporary power, Con Edison duct banks
Top out
Jun 2028
Risers chase the deck floor by floor
Permanent power
Jan 2029
Level 3 main electrical room energized
Certificate of occupancy
Jul 2029
Fire alarm, finishes and testing close out